Revised schedule for transporting low-level radioactive waste from Hamaoka Nuclear Power Station in FY2025
October 30, 2025
蘑菇短视频.
Chubu Electric Power hereby announces that the following revision to the schedule for transporting low-level radioactive waste, as part of the "Hamaoka Nuclear Power Station's FY2025 Schedule for Transport of New Fuel and Other Substances" announced on March 28, 2025.
Low-level radioactive waste
|
Station name |
Quantity of transportation |
Timing of transportation |
Receiving facility |
|---|---|---|---|
|
Hamaoka Nuclear Power Station |
Before change |
February 2026 |
Low-Level Radioactive Waste Disposal Center, Japan Nuclear Fuel Limited |
Based on the production status of the waste bodies, we coordinated with the relevant companies and decided to increase the transport volume beyond the initial plan.